⟩ When it is your responsibility to organize and plan a project what steps do you take?
Answer should show preparation and focus when using organizational skills. Applicant should be able to prepare narrowly focused project plans.
Answer should show preparation and focus when using organizational skills. Applicant should be able to prepare narrowly focused project plans.
The Final technical authority of a project lies with A. Assistant Engineer B. Executive Engineer C. Superintending Engineer D. Chief Engineer
Performance of a specific task in CPM, is known A. Dummy B. Event C. Activity D. Contract
Construction schedule is prepared after collecting A. number of operations B. output of labor C. output of machinery D. quantity of various items E. all the above
Pick up incorrect statement from the following A. The activity is the time consuming part of a project B. The beginning and end of a job, are called events C. The activity which consumes maximum time, is called a node D. Logically and sequentially connected activities and events form a network E. None of these
Dummy activity A. is artificially introduced B. is represented by a dotted line C. does not consume time D. all the above
The Time and progress chart of a construction, is also known as A. Bar chart B. Gantt chart C. Modified Mile stone chart D. Critical path method chart E. All the above
Pick up correct statement from the following A. The float may be positive, zero or negative B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project D. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project E. All the above.
Milestone chart A. shows the inter-dependencies of various jobs B. depicts the delay of jobs, if any C. points outgoing ahead of schedule of jobs, if any D. none of these.
Completion of activity on CPM network diagram, is generally known A. Event B. Node C. Connector D. All the above.
Overall in-charge of an organisation at the site responsible for the execution of the works, is A. Executive Engineer B. Engineer C. Junior Engineer D. Sub overseer E. Assistant Engineer