⟩ Dummy activity A. is artificially introduced B. is represented by a dotted line C. does not consume time D. all the above
D. all the above
D. all the above
The Critical path method A. is an improvement upon bar chart method B. provides a realistic approach to daily problems C. avoids delays which are very common in bar charts D. was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957 E. All the above
Critical path lies along activities having total float A. positive B. negative C. zero D. same
Salient feature of functional organisation is A. strict adherence to specifications B. separation of planning and design part C. each individual maintains functional efficiency D. work is properly planned and distributed E. all the above
Difference between the time avail-to do a job and the time required to do the job, is known as A. event B. float C. duration D. constraint
The site order book is used for recording A. instructions by the executive engineers B. construction measurements C. issue of store equipment's D. names of the casual labour
Payroll Management Interview Questions Part 1
Payroll Management Interview Questions Part 2
Payroll Management Interview Questions Part 6
Payroll Management Interview Questions Part 5
Payroll Management Interview Questions Part 4