⟩ What steps do you take to organize and plan a project?
Answer should show preparation and focus when using organizational skills. Applicant should be able to prepare narrowly focused project plans.
Answer should show preparation and focus when using organizational skills. Applicant should be able to prepare narrowly focused project plans.
Bar charts are suitables for A. minor works B. major works C. large projects D. all the Above
Estimated time required to perform an activity, is known as A. event B. dummy C. duration D. float
If total float and duration of an activity are 5 and 10 days respectively, the particular activity can be A. started 5 days later B. completed 5 days later C. performed at slower rate in 15 days D. all the above
The Modular co-ordination of construction means proper A. planning B. designing C. execution D. all the above
Which one of following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast E. all the above
Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as A. duration B. total flat C. free float D. interfering float
Artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as A. event B. free float C. dummy D. constant
Time which results in the leasi, possible construction cost of an activity, is known A. normal time B. slow time C. crash time D. standard time
CPM family includes A. CPA (Critical Path Analysis) B. CPP (Critical Path Plotted) C. MCE (Minimum Cost Expenditure) D. CPS (Critical Path Scheduling) E. All the above
Pick up correct statement from the following A. CPM analysis is activity oriented B. PERT analysis is event oriented C. CPM does not make any allowance for the uncertainties in the duration of time D. In CPM, the time is related to cost E. All the above